City of Grand Junction issued the following announcement on Sept. 11.
City of Grand Junction Projects with Travel Restrictions
Riverfront at Dos Rios Phase 2 Project (8/17/20 to 6/17/21)
- Be aware of construction activities around the bicycle playground, access to the bike park from Riverside Parkway will remain open during construction.
- The existing asphalt surface of Riverside Drive, south of Hale Avenue, has been permanently removed. No vehicle access shall be allowed south of Hale.
- The River Front Trail, south of Hale Avenue, shall remain open, but expect small detours around construction activities through September.
- Elm Avenue from N 18th Street to N 23rd Street
- Elm Avenue closed to through traffic
- Resident access provided
- Anticipated Completion; Late September
- 12th Street and 13th Street closed to through traffic
- Anticipated Completion: Mid October
- Tuesday, September 15th: G Road will be closed at Victor Drive
- Detour route will be in place
North Avenue Gas Line Replacement Project Phase 2, between 28 Road and 29 3/4 Road – Xcel Energy
- Work hours – 8pm to 8am Sunday thru Thursday
- Expect lane closures and delays
- Alternate route advised
- White Avenue will be open to traffic this week between Rice Street and 1st Street.
- Night work on 1st Street involving lane closures between Grand Avenue and White Avenue, 7 p.m. – 7 a.m.
- West bound lane closuer on Hwy 340 at the Colorado River bridge, 9 a.m. – 4 p.m.
- Business access provided
- Alternate route advised
- F Road from 31 1/2 Road to 32 Road
- Expect delays
- Alternate route advised