Quantcast

Grand Junction Times

Saturday, September 21, 2024

CITY OF GRAND JUNCTION: Projects Affecting Traffic for the Week of 12/7/2020

Img 08062020 115121  1000 x 667 pixel

City of Grand Junction issued the following announcement on Dec. 4.

City of Grand Junction Projects with Travel Restrictions

Riverfront at Dos Rios Phase 2 Project (8/17/20 to 6/17/21)

  • Be aware of construction activities around the bicycle playground, access to the bike park from Riverside Parkway will remain open during construction
  • The existing asphalt surface of Riverside Drive, south of Hale Avenue, has been permanently removed. No vehicle access shall be allowed south of Hale
  • Riverfront Trail may be closed at times. Follow well-marked detour around construction activities
Annual Leaf Removal Program - City Wide

  • Please slow down and use caution in areas where City Crews are working
  • Anticipated Completion – Late December
Hale Avenue - Utility Work

  • Hale Avenue will be closed between Park Avenue and Lawrence Avenue
  • Detour route will be in pace
  • Anticipated completion - Mid to late December
Non-City of Grand Junction Projects with Travel Restrictions

E Road Reconstruction between 31 Road and 32 Road - Mesa County

  • Expect full road closures with a well-marked detour route at various locations
  • Resident access will be maintained
  • Alternate route advised
  • Work hours: Monday thru Saturday, 7 a.m. to 7 p.m.
  • Anticipated completion: September 2021
33 ½ Road Irrigation Project, between D ½ Road and E ¼ Road – Mesa County

  •  Expect full road closures with well-marked detour route in place
  • Resident access will be maintained
  • Alternate route advised
  • Work hours: Monday – Friday, 7am to 5pm
  • Anticipated Completion: December 31
ADA Ramps Phase III - Mesa County

Monday, Dec. 7 to Friday, Dec. 11 work will consist of:

  • Westbound right lane closure on Riverside Pkwy. and US 50 off ramp
  • Westbound right lane closure on Main St. from 24th Ct. to 21st St.
  • All intersections will maintain public access
  • Expect intermittent flagging during construction
  • All work is tentatively scheduled based on weather conditions
Hwy 340 Culvert Project - CDOT

  • Work is scheduled to begin Dec. 10 and is expected to last until mid June
  • Motorists can expect minimal traffic impacts with occasional single lane closures
  • The bike path will have occasional stops with possible dismount and walking your bike through the work
  • Normal working hours will be Monday through Friday from 7 a.m. to 5 p.m.
Original source can be found here.

ORGANIZATIONS IN THIS STORY

!RECEIVE ALERTS

The next time we write about any of these orgs, we’ll email you a link to the story. You may edit your settings or unsubscribe at any time.
Sign-up

DONATE

Help support the Metric Media Foundation's mission to restore community based news.
Donate

MORE NEWS